"CTRA/PSU - Kemayoran Citra Office Towers - Jakarta - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "CTRA/PSU - Kemayoran Citra Office Towers - Jakarta - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.
Scope
The project involves the construction of two 28-story, 43,000m2 office buildings on 1.7ha of land in Jakarta, Indonesia.

The US$164 million project includes the following:

1. Construction of a three-story, 13,000m2 retail podium

2. Construction of meeting rooms

3. Construction of conference rooms

4. Construction of restaurants

5. Construction of parking and related facilities

6. Installation of elevators

7. Installation of safety and security systems
Summary
Ciputra Development Tbk PT (CTRA), a subsidiary of Ciputra Group, and PT Pembina Sukses Utama (PSU) are undertaking the construction of an office complex in Jakarta, Indonesia.

The project involves the construction of two 28-story, 43,000m2 office buildings on 1.7ha of land.

It includes the construction of a three-story 13,000m2 retail podium, meeting rooms, conference rooms, restaurants, parking and the installation of elevators, safety and security systems.

On November 28, 2014, an official groundbreaking ceremony was held.

Sigmatech Tatakarsa has been appointed as a mechanical and electrical engineer, Dyxy as Lead Architect, PT Anggara as Local Architect, PT Wiratman as Structural Engineer, PT Langdon Seah as Quantity Surveyor and PT. Multibangun Adhitama Construction and PT. Nusa Construction as the construction contractor.

In September 2015, design and foundation works are underway.

In January 2016, foundation works completed.

On March 8, 2018, topping off ceremony held for the north tower which comprises 407 units of strata title office space.

Construction works on north tower are underway and expected to be completed by the fourth quarter of 2018.
Reasons To Buy
• Gain insight into the project.

• Monitor the latest project developments.

• Identify key project contacts.
Key highlights

Table Of Contents
1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix
close

category