F.L. Wind d.o.o. (FLW) is constructing a wind farm in Tomislavgrad, Bosnia and Herzegovina.

The project involves the construction of a 36MW wind farm. It includes the construction a substation and related infrastructure, the installation of 18, G97-2.0 MW wind turbines, generators and transformers, and the laying of transmission lines.

A3 doo za has been appointed as a construction contractor.

In August 2017, construction works commenced.

In February 2018, Siemens Gamesa appointed to supply, operation and maintenance contractor.

As of March 2018, construction works are underway and scheduled to be completed by the fourth quarter of 2018.
1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Scope
6.Description
7.Latest update
8.Background
9.Key Contacts
10.General News, Project News
11.Appendix
close

category