Synopsis
"PLN - Kaltim II Peaker Gas-Fired Power Plant 100 MW - East Kalimantan - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.
The "PLN - Kaltim II Peaker Gas-Fired Power Plant 100 MW - East Kalimantan - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.
Scope
The project involves the construction of a 100MW (2x50MW) peaker gas-fired power plant in East Kalimantan, Indonesia.
The US$80 million project includes the following:
1. Construction of a powerhouse
2. Construction of coal storage tanks
3. Construction of combustion chambers, steam generating units
4. Construction of a pipeline network
5. Construction of chimneys and cooling towers
6. Installation of turbines
7. Installation of generators
8. Installation of turbines
9. Laying of transmission lines
Summary
PT Perusahaan Listrik Negara (PLN) is undertaking the construction of Kaltim II peaker gas-fired power plant project in Indonesia.
The project involves the construction of a 100MW (2x50MW) peaker gas-fired power plant, a powerhouse, coal storage tanks, steam generating units, pipeline infrastructure, cooling towers and chimneys, the installation of turbines, generators, and transformers, and the laying of transmission lines.
The project is being funded by Asian Development Bank (ADB) towards the cost of Sustainable Energy Access in Eastern Indonesia- Power Sector Generation Program.
On February 9, 2017, PLN invited tenders for the engineering, procurement, and construction (EPC) contract with submission deadline April 12, 2017 and extended to July 7, 2017.
Reasons To Buy
• Gain insight into the project.
• Monitor the latest project developments.
• Identify key project contacts.
Key highlights
Table Of Contents
1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix